Hi fiends,

We are doing implementation for Public Sector with EA-PS, MM and PS (ECC 6.0).

We are having problems in the control availability or commitments of the WBS: duplication of the commitments in WPS:

- In EA-PS create a Funds Commitment (FMZ1) : 10u20AC

- In MM create a Purchase order: 10 u20AC

In our model the committed should be 10 u20AC instead of 20 u20AC.

We need that the Pruchase order don't consume budget in the WBS.