Confirming activity results in rescheduling

Hi Experts,

When confirming activities that have relationships I am getting the network rescheduled... Automatic rescheduling check is off.

Can anyone help on this?

Thanks.

Neil

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

3 Answers

  • avatar image
    Former Member
    May 16, 2009 at 09:32 AM

    Hi,

    Please check the shift order tick applied in OPU6.

    OR

    Is the requirement like not to re-schedule activities once scheduled after mentioning start and end dates in network?

    Sam

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Zhenbo Wang

      Hi Zhenbo,

      Thanks for the tip but I see two main problems here:

      1. My main concern is the difference of one minute on the scheduling when the task is released or when it is partially confirmed. Why is the system using different basis to calculate when the duration has not changed? Neither the earliest start date nor the latest finish date change, only the earliest finish and the latest start dates. I was reading the note you suggested (VERY interesting by the way) but could not find an explanation for it.

      2. Using SAP PS help.sap.com

      When is Scheduling Carried Out?

      A network is scheduled:

      If you create a network.

      If you call up the schedule function.

      When you save the network, depending on whether you have set the Schedule automat. indicator in the network header.

      If you release the network, the indicator is set automatically and the network is scheduled each time you save it.

      If you have made a change relevant to scheduling - for example, changed a duration in the activity or a relationship - and then have saved the network. *This function depends on the settings you made in the scheduling parameters (Schedule automat. indicator).*

      If you make changes in the network which are relevant to scheduling, the system automatically sets the status "Dates are not updated" (NTUP).

      May this lead to an OSS message?

      Thanks a lot for your help, I'd really appreciate any suggestion about this.

      Kind regards,

      Neil

  • avatar image
    Former Member
    May 28, 2009 at 08:32 AM

    Hi,

    Just for your information, does not matter whether automatic scheduling is on or off, whenever you set dates on the dates tab, recheduling is done.

    Do you know any way to do a partial confirmation programatically without setting real dates on the tab?

    Thanks in advance.

    Kind regards,

    Neil

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Jun 09, 2009 at 02:42 PM

    Followup in a different thread...

    Add comment
    10|10000 characters needed characters exceeded