Hi,
We have configured Contract_Manufacturing_Procurement scenario in which ECC sends PO (IDoc PORDCR102) to XI and from XI it is posted to SNC7.0. PO is visible on SNC and when supplier confirms PO manually on WebUI it should send confirmation back to ECC. But due to some reason SNC(SCM) is not triggering outbound message ReplenishmentOrderConfirmation_Out. Any idea?
End to end Scenario:
1) ECC -> XI -> SNC
PORDCR1.PORDCR102 ->ReplenishmentOrderNotification_In (Working fine)
2) SNC -> XI -> ECC
ReplenishmentOrderConfirmation_Out -> ORDRSP.ORDERS05 (Not working) ?????????
Let me know any input.
Nilesh