Settlement of Production order:Issue

Former Member
0 Kudos

Hi experts,

At the time of running CO88,following error comes:

Internal error in FORM/FUNCTION get_corresponding_mbew(saplck88) in position 10 with RC

Message no. C+099

Procedure

Please inform your system administrator.

Please advise.

Regards,

Samar Ghosh

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

not answered

Former Member
0 Kudos

Hi experts,

In SAP notes 484027,it is mentioned:

Solution

The following options are available as a solution:

1. If you already know the stock into which the order delivers, then you can post a fictitious goods receipt of the order into the corresponding stock.Afterwards, you can cancel the goods receipt before you execute the settlement.

2. If the corresponding stock is unknown, but you have to settle the order nonetheless, then you have to change the settlement rule.For example, the settlement can be made to a cost center instead of a material.

Please advise.

Regards,

Samar

Former Member
0 Kudos

HI,

see SAPNET note 484027, did you made this note search before you post this thread?

Best regards, Christian