Hello Guru,

in planned order, how could i can check if this planned order has enough capacity to be converted into a production order?

when i go to capacity leveling in my planned order path is GOTO---CAPACITY LEVELING there a pop up screen settings for capacity planning in Planning type i choose Deatailed Planning in Buckets it was Days

Thanks

Edited by: SAP_PHIL on May 11, 2009 10:03 AM

Accepted Solutions (0)

Answers (2)

Answers (2)

rupesh_brahmankar3
Active Contributor
0 Kudos

Dear,

You can check in CM52 or CM01- work center wise before that you need to run MRP with lead time scheduling. And check OPPQ setting I told you in previous posting.

Regards,

R.Brahmankar

Former Member
0 Kudos

hi how could i closed this?

Edited by: Ryan on Jun 29, 2009 6:49 AM

Ritz
Active Contributor
0 Kudos

Ryan,

In the top of your post , you have option to selct your thread is answered.

and it will be great , if you allot points while closing the thread to the memebers who helped you.

Regards

Ritesh

Former Member
0 Kudos

Hi

In MD12

Click on Edit > Capacity check

Regards

Brahmaji