i want to ask question , in my task ,i cant change task status .at the change status of task .it cannt edit. please help me .but the phase and project change status can edit.

Accepted Solutions (0)

Answers (1)

Answers (1)

francesco_pezzoli
Active Participant
0 Kudos

Hello Tom,

Are you referring to a System Status or to a User Status?

In case it is a user status, maybe you need to consider the logic which is mentioned in Knowledge Baste Article Nr. 2546072.

In case you are referring to a system status, maybe you are unable to edit the task status because the status on the superior opbject is stopping you from doing so? e.g. you may need to undo "Completed" on the superior phase before you can undo it on the task itself.

If the above does not help (or apply to your scenario), please provide more details about the reported behaviour.

Best regards

Francesco