cancel
Showing results for 
Search instead for 
Did you mean: 

No Expenditure Items found for Inquiry during DP81

Former Member
0 Kudos

Dear All,

I am trying to generate PS Quotation from the transaction DP81. System gives me the below error.

No expenditure items found

Message no. VPK1310

Diagnosis

No expenditure items matching the selection were found.

System Response

No processing possible.

Procedure

Resource-related billing contains no expenditures for the posting timeframe you specified. Specify a different timeframe.

In the case of quotations, there are no costs in the project or service order. Check whether any have been planned.

I have assigned the WBS in the Account Assignement Tab and I have also assigned the standard 1300000 DIP profile in the Sales B tab. In the condition tab EK01 Condition type remains in Red.

Kindly help me get rid of this error.

Regards,

Saravanaa.S

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Dear All,

My query is solved.

I was required to run the transaction CJR2 for the respective WBS element.

Thankyou all.

Regards,

Saravanaa.S

Former Member
0 Kudos

Dear,

I have the same problem as the transaction DP82 doesn't see the cost which come from network planning as it's only see the cost from the transaction cjr2 ???