Strategy 50- Assembly's Dependent Requirement Grouping

25 Views

hi Gurus,

MRP settings of materials I am using is as under

1.FG--


Strategy-50-----Availability check: CH -


Indiv Collec ind : 2 ---Consumpt mode : forward/ backward with 30 days each

2.-- Level-1 SFG --


Strategy-50 -


Availability check: CH -


Indiv Collec ind : 2 ---Consumpt mode : forward/ backward with 30 days each

3.--


Level-2 SFG
No Strategy
Availability check 02---Indiv Collec ind : 2 ---Consumpt

My requirement is to maintain PIR for level-1 SFG...after providing PIR of SFG level-1 and performing MRP run. Planned orders are created agains the dependant requirement of Level-2 SFG which are drawn from PIR of SFG level-1. Using strategy50 i m not able to convert planned orders of SFG-Level 1 into process order on the other hand Planned orders of SFG level-2 are convertible into process order, which is the desired functionality.

Now if i create a sales order of the FG following results appear.

at SFG level-1

- Unconvertible Planned Orders created remain unchanged.

- PIR is not effected

- Depandant requirement is created for the quantity exploded from FG sales order and corresponding planned order is also created which is convertible.

"Desired result is: PIR of SFG level-1 should be consumed "

at SFG level-2

two seprate planned orders are created, one against the PIR of SFG level-1 and second agains the dependant requirement of the sales order created for FG ( i.e. FG--> SFG level -1 > SFG level >2)

Desired Result is

one netted off planned order to be created at this level..i.e. the planned order quantity should be increased only if the dependant requirement of sales order exceeds the dependant requirement coming from PIR of SFG level-1.