Hi,

Please can you explain to me the process of rework orders and the cost, Once the product has been put into stock and the recovery of labour and materials have been processed, what costs are contributed.

Thanks

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

thanks

Former Member
0 Kudos

Hi,

first creat header order & confirm it

while confirming (say for example order quantity is 10, then in confrimation give as 8 & in rework field give 2)

creat reference operation set by CA11

now go to CO07 & give material descrption & give quantity as 2

now system will giev a pop-up, in that give ur refernce operation set number

then system will take u to settelment recevier

here give ur header order number, then insert components.

then confrim ur rework order

now take GR for ur header order

NOTE:there will be no GR for ur rework order

regarding costing, settlement will be done for header order

revert back still for furthur info

Regards

kumar

Former Member
0 Kudos

Jessica,

Follow the links given,

Hope this helps you.

SmanS

Former Member
0 Kudos

Thanks for the attachments but I dont think this is what we need. When we are doing a rework order it is normally due to errors with the product, ei Incorrect label. As that we donot create the rework order using the original process order number. We create the rework order booking from stock. Can you let me know how this will affect our Labour and Material variances?

Former Member
0 Kudos

Hi

If your doing any kind of rework that always with some produce products. For this you need some components to get final product and your machine or labor involved.

For costing percepective if your asking always this is book with parent order as settlement rule. if order is not available then you can use cost center. This correct way to capture actual material and labor cost incurred to produce the product.

Plz ask if any doubt.

Regds,

Rajesh

Former Member
0 Kudos

Thanks, If we do rework order for product, does the stock value get written off in scrap? If so once you reconfirm after rework, do you then get the material and labour recovery again?