Project

Former Member
0 Kudos

Hi Experts

How to change project profile from exiting to new profile.

Thanks In advance

Ragini

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

You can not change project profile once project is saved.

Regards,

Answers (4)

Answers (4)

stheurkar
Active Contributor
0 Kudos

Hi,

You can change project profile at database level with the help of abaper.But condition is that no FI posting should happen.

Project profile field gets stored in PROJ table.

For this you can discuss with your abaper in more details.

Sandeep

former_member711289
Participant
0 Kudos

Hi Ragini once the project is created u can only delete it . you cant modify that. If it is released and having some cost than more complicated.

Regards

Abhishek Sinha

Idhasoft, India

Former Member
0 Kudos

Hi All

i know this once saved it is not possible for changes..is there any changes through technicaly?

MTerence
Active Contributor
0 Kudos

Hi

There is no possibility in this.

Since this is place u create a project.. its user side..

- Pithan

Former Member
0 Kudos

Hi ,

access table PROJ thru se16n

before executing type command &sap_edit and enter system will give message sap edit activated

then execute

Change ur project profile as u want and save.this is ur doing direct changes in table.

Generally it is not recommended to use &sap_edit just check the corresponding impacts and use.

Hope this solve the issue.

Rgds

Former Member
0 Kudos

hi...

 u need to change the profile becoz u want to change some organisation parameter , plan/budget profile. so most org parameters except co area can be changed by mass change function and plan/budget profile also be changed later. which will a virtual change in ur project profile. 

ashis

MTerence
Active Contributor
0 Kudos

Hi

I dont think its possible to change the project profile, once it was Saved.

Try to create a Project definition with a new Project Profile

- Pithan

stheurkar
Active Contributor
0 Kudos

Hi,

If any FI postings are not happened delete the project. Again create new project with right project profile.

Once project is saved you can't change project profile.

Sandeep

Edited by: Sandeep Theurkar on May 6, 2009 12:35 PM