Dear QM Experts,
Scenario and Requirement
1. There are few incoming materials for which every inspection lot has to be skipped.
2. This control is required for specific vendor material combination wise.
3. Elaborately this may possible that for material 123000 there are 2 vendors ABC and XYZ. Out of which all inspection lots those come from ABC only have to be skipped while for XYZ vendor inspection lots should be created in REL mode.
Queries
1. Can we fulfill this requirement by DMR at lot creation?
2. Since there are no parameters that client want to inspect should we use DMR without task list?
3. First inspection lot should be skipped. Whether it is must to create quality levels manually for the first time?
4. Can anybody brief the step by procedure to fulfill this requirement?
Thanking you
Best Regards,
Anand Rao