on 05-04-2009 1:05 PM
Hi Team,
In one of the client specific scenarios the Requisitioner of the SCart can only do the Desktop confirmation for the SCart created by him.
1.What's the standard SRM working methodology for Desktop confirmation ?
2. Now there is requirement with reference to the above mentioned client that the The Requisitioner has created a Scart and it's completed and PO is also created.
because of some reasons the existing Requisitioner is delimited and the new User is assigned for the same position.
how could you do the desktop confirmation with the New user ?
Regards,
Adinath Raykar
Hi,
Change the Requester and Goods Recepeint fields in PO and order the PO again. The changed requester should be able to do confirmation now.
Regards,
Sanjeev
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.