Hi guys,
I am creating a PM Order manually can anybody tell me :
How can assign the relationship such as succeesder and predecessor.
AR
Amit,
Go to the operation tab and select an operation. Select one of the buttona a the bottom of the screen e.g. Internal
At the botton of the next screen you should see a sub-tab called Relationships. Enter your required data here.
PeteA
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Easy way to Relating is
In Order ,, GOTO -- Graphic -- Network Structure , You will get all Opertions mentioned in order , Check for "Change"button , you will get Pencil Like ICON then on Graphic draw line as you want FS , SS ,FF & other Relation.
You Can Mention dates & Other things , Its Very easy Compared to mentioning in Order Internal Tab.
check it
Regards,
Srinivas
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
103 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.