cancel
Showing results for 
Search instead for 
Did you mean: 

Change Cost Center Valid To Date

Former Member
0 Kudos

Hi,

I want to change cost center valid To date. Please let me know which t code I use for that. Thanks in advance.

Thanks & Regards,

Hemant Maurya

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

You can change cost cener validity by creating new cost center through t.code KS01 with reference to same cost center.

Ex. suppose you have created cost center 5009000000 from 01.07.2005 to 30.06.2006. Now you want the same cost center to be created from 01.07.2006 to 31.12.2009.

So, Go to KS01 and put this CC code and Valid From to To Date as 01.07.2006 to 31.12.2009. Also put same CC code with CO area in reference. The same CC will be created with all required information. Also If profit center is required field in your CC, then first of all you need to extend your profit center through KE52 t.code.

Pls get back for further query.

Thanks & Regards,

Taral Patel

Answers (0)