MRP

Former Member
0 Kudos

Dear all,

client has abt 8 plants

now they are running MRP background

now my point is how to check, (at what time they are running MRP in background)

in which t-code i should check

Regards

kumar

Accepted Solutions (1)

Accepted Solutions (1)

former_member196398
Active Contributor
0 Kudos

Kumar,

In transaction MDBT, you select the variant and click display scheduling. Or else you can go to SM37, give the Job name if you have or the MRP program name and search.

Regards,

Prasobh

Former Member
0 Kudos

Hi thanx to both of u ,

now i have already done what u have said (MDBT)

now i want to know one thing

1-in status i have options released & finished ( what is the difference between this two)

Regards

kumar

rupesh_brahmankar3
Active Contributor
0 Kudos

Dear,

When you create the job then give the scheduling date then its status become released.

Before completing the exeution of the program in which you are calling the job is waiting till the job completes the processing.

And when it become finish then status become Finished.

In MDBT transacton choose the variant & then click the "Display scheduling" tab. Check the status against the date, if it is "Finished". Then choose this row & click results.

Now choose the ABAP List icon under "Type". Here the MRP run result will be displayed.

Hope clear to you.

Regards,

R.Brahmankar

Former Member
0 Kudos

thanx Brahmankar,

after clicking results it is taking me to

output controller: spool request slection screen

after this i am unable to proceed

pz help me to proceed forward

Now choose the ABAP List icon under "Type". Here the MRP run result will be displayed

how to proceed with ur above input unable to understand

how to check the results

Dear Brahmankar or any other experts

plz look into the issue & help me to move forward

Regards

kumar

Edited by: kumar kumar on May 1, 2009 8:15 AM

Edited by: kumar kumar on May 1, 2009 8:38 AM

Former Member
0 Kudos

Dear Bramankar,

actually i am looking for this plant below

varaint

BINOLA

and variant descrption is

MRP Run for BINOLA

afetr this i clicked this varaint & clicked show scheduling

then the results showing for other plants (but could'nt find the result of BINOlA palnt)

what could be the reason

Regards

kumar

Former Member
0 Kudos

dear all,

in MDBT, i am looking for a particular plant results

but it is showing as this

Plant - 1070

Processing key - NEUPL

Create purchase req. - 3

Schedule lines - 3

Create MRP list - 1

Planning mode - 3

Scheduling - 1

Planning date - 00.00.0000

now here planning date is 00.00.0000

does it mean no MRP planning is taking place in this particular plant

Plz let me know

Regards

kumar

rupesh_brahmankar3
Active Contributor
0 Kudos

Dear,

If no mrp take place then you will not get any result.

First check wheather background MRP run schedule and take place for that plant.

Regards,

R.Brahmankar

Former Member
0 Kudos

Thanx Brahmankar,

Plz let me know how to check

plz request u to help me step by step

Plz confirm one thing

as i said planning date is 00.00.0000

this means MRP is taking place or not

just confirm this

Regards

kumar

Edited by: kumar kumar on May 1, 2009 9:32 AM

rupesh_brahmankar3
Active Contributor
0 Kudos

Dear,

Please check MD05, put material and plant and enter, it will show u the last MRP list.

in the header line you will find out the when MRP carried out last.

I hope requirement solved by this.

Regards,

R.Brahmankar

Former Member
0 Kudos

Thanx very much Brahmankar,

can i know by which transction (MD01 or MD02 etc)

by tranction MD05

because i have in putted one header material in MD05 & executed

it's showing as

MRP list as of 07:02:2009, 00:04 Hrs

can i know in which transctaion this MRP run has taken place

Regards

kumar

Edited by: kumar kumar on May 1, 2009 9:48 AM

former_member196398
Active Contributor
0 Kudos

Kumar,

Use transaction STAD or STAT i think to check who has run the last MRP related transaction. You can work with your basis guy on this

Regards,

Prasobh

rupesh_brahmankar3
Active Contributor
0 Kudos

Dear,

If you are running manually - you can see the data in MD05, Special MRP list data tab page.- this will give the last MRP run date

If you are running in background, then in MDBT transaction, findout the background job on which this material is planned and click on show scheduling...this will give the MRP run date. If there is no data means not schedule it.

Hope clear your doubts.

Regards,

R.Brahmankar

Former Member
0 Kudos

once again Thanx to both of u ,

i am unable to get from which transcation MRP has taken place

if i want to set again MRP in back ground job

what are the steps required for that

should i delete old variant &

again set new varaint & schedule

or else can i do fresh MDBT with old variant which has been already created

Plz let me know step by by step &

Plz let me know how to process with SM37

Regards

kumar

kaushik_choudhury2
Active Contributor
0 Kudos

Hi Kumar,

You can excute the MRP in background mode through MD01,MD02 or which ever T-code you are using the menu path Program -> Execute in background .

You can check the result (when it started , Status, Time taken etc) in SM37.

You can also use SM36 to schedule the MRP to run at particular time with the variant required . Do let us now if you need any further information on the same

Thanks

Kaushik

Former Member
0 Kudos

Hi Kaushik,

thanx very much

now plz let me know how to check in SM37

i have seen in MDBT report as (RMMRP000) for a particular plant

i think by this (RMMRP000) i can check in SM37,

results of that particular plant right ??

plz explin me step by step how can i check in SM37

Regards

kumar

Edited by: kumar kumar on May 1, 2009 11:54 AM

kaushik_choudhury2
Active Contributor
0 Kudos

Hi Kumar,

I don't have access to SAP right now .........so will just elucidate the steps with the screens from my memory ..(there may be some deviation )

Execute SM37. Check the check box released , Active , Scheduled & other status for which you are interested ,

If you have executed the program in background with your user ID then put your user ID. If you are not sure then put *.

In the program name put * (if you know the program then put that). Set the from & to date range as today's date . Then press F8.

Do let us know if you need any further information/ face any issue on the same

Thanks

Kaushik

Former Member
0 Kudos

Kumar,

In SM37, select the mentioned programe, click on GOTO--- Step Overview.

In the next sceen select the programe name & follow GOTO---- Programme documentation.

Check & revert.

SmanS

Former Member
0 Kudos

Hi Kaushik,

once again thanx

just let me know one thing

right now i am doing in "production server"

now confrim one thing to me is SM37 is to check only the results or

we can even sehedule the job

the reason of my asking is as i am doing in production server

it should creat any problem

Plz confirm

can i go ahead with ur suggestion

Regards

kumar

Former Member
0 Kudos

Hi,

in GOTO header i cannot find step overview

Regards

kumar

Former Member
0 Kudos

Dear Prasobh,

can u plz let me know the below

right now i am doing in "production server"

now confrim one thing to me is SM37 is to check only the results or

we can even sehedule the job

the reason of my asking is as i am doing in production server

it should creat any problem

Plz confirm

Regards

kumar

Edited by: kumar kumar on May 1, 2009 1:27 PM

Former Member
0 Kudos

Dear all,

can anyone look this

Regards

kumar

kaushik_choudhury2
Active Contributor
0 Kudos

Hi Kumar,

Transaction SM37 is only to check the batch job status ............so you can go ahead and excute the same ...............

To schedule the job we have SM36 in place

Thanks

Kaushik

former_member196398
Active Contributor
0 Kudos

Kumar,

SM37, can be used for multiple purpose.

1. If a Job is scheduled in SM36, you can select the Job of status "Scheduled" and click on the green flag to release before the scheduled time.

2. Within SM37, you can copy any existing job and that you can release(Run).

3. You can check the jobs current status

4. You can display the Spool of the Job which got completed.

5. You can select the job and click steps to display the Variant and Program details used for the Job.

6. You can stop a Job and Also can delete a Job Log or Scheduled Job

Regards,

Prasobh

Former Member
0 Kudos

Hi,

thanx to Prasobh, Brahmankar, Kaushik, & SmanS

as today i am not at client site

but yes many problems are there regarding MRP at client site

so will updated them, when i go there

as of now closing the thread

once again Thanx to u all

Regards

kumar

Answers (1)

Answers (1)

rupesh_brahmankar3
Active Contributor
0 Kudos

Dear,

The program is RMMRP000.

In transaction SM37 the status of the background job can be seen.

Here you can check the details of back ground MRP run Details.

Else you can also check in MDBT select the variant and click on schduling.

Regards,

R.Brahmankar