on 04-30-2009 7:10 PM
Sir,
once po is released it is should not be allowed to edit.
how can i configure this
regards
amey
You can configure the release indicator to be not changeable with change key "1". This will prevent any changes to the PO once it is released.
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Amey,
Once PO is released it cant be Changed it can be done by doing the following setting in SPRO.
SPRO>Material Management>Purcahsing->Purchase order->Release procedure for purchase order--->Define release Procedure for the PO
In this Release Stategy config there is option called Release indicator
where in we have to define a release ID and this release ID ( Eg A ) has to be given 1 cannot changeable in the feild in chagble--for the allowing no changes in PO after release and then we have to go to release Strategy option we can select the release strategy we want the change and in the Strategy
click on the release status and in this status we can give the ID defined earlier ( at which level what effect should come)
hope so it helps
regards
Anjanna.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.