on 04-30-2009 9:39 AM
Hi all,
How to disable the auto approval when user change the contract when the contract is waiting for approval? Is this a SRM bug ?
Step:
1. Process contract -> Create a Contract
2. Add an approver -> press button release -> this contract is waiting for approval
3. Process contract -> Change the contract detail I.e. Title. -> Press Release
4. Check approval review, this contract is auto approved.
I check from swi1, i found below item
Automatic approval for Contract no. Outline Agreement 4400000043, GUID F0AEF94996431374E10000000AB3386A
This item executed using WF14000086
Best regards,
Xiang Li Heah
Edited by: xiangli heah on Apr 30, 2009 10:52 AM
Hello
go to the swb_cond transaction, and deactivate the start condition for the WF14000086
business object of Contract, event is CHANGEVERSIONSAVED.
Daniel
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.