Periodic work schedule error

Former Member
0 Kudos

When i am defining the period work schedule (time management), it's say that daily work schedule does not exist for work schedule 01?

i had created already WBS & DWS.

Khan

Accepted Solutions (1)

Accepted Solutions (1)

sikindar_a
Active Contributor
0 Kudos

Check T551A or PWS thru SM30 V_T551A

and T508A

Edited by: Sikindar on Apr 29, 2009 4:23 PM

Answers (5)

Answers (5)

Former Member
0 Kudos

The DWS grouping was 01 and my PWS was for 02..

Former Member
0 Kudos

Hi Sajkhan,

Check whether 01 is defined and grouped properly in the Personnel subarea grouping (Group Personnel Subareas for the Work Schedule, Group Personnel Subareas for the Daily Work Schedule).

Also check whether the WBS & DWS you have created is under grouping 01 and when you create PWS make sure the grouping is 01 too.

regards,

Santhosh

Former Member
0 Kudos

the problem is solved, the dws was not on my default grouping..

thx for every1 who tried to help me out.

Former Member
0 Kudos

Check grouping in V_T550A

Former Member
0 Kudos

Hi Khan,

Also check the grouping PSR and WS and check whether you have WS for the specified group as Revathi said.

thanks,

Vasu.

former_member583520
Active Contributor
0 Kudos

HI,

Have you assigned PWS to Dw.

Pls check that for 01.

Thanks nd Regards,

Revathi.