We are doing our costing run CK40N for our finished goods materials. Initially I had configured operation scrap in various BOMs to allow MRP to plan for extra raw materials and semi-finished good used up by sampling and rejects, however the accountants are not happy that the planned scrap inflates the costs of the the finished goods and insisted that we remove it.

Is there a way to get costing to ignore operation scrap while still including it in the BOMs for MRP purposes?