Apr 29, 2009 at 08:11 AM

ROH and HALB planning in MF50

39 Views

Hi,

I have one issue. I have a customer order but BOM has not been finalised. in other words materials have been created but some ROH has not been added in the BOM.

But I need to procure those ROH but only against the requirement of Sale order. So how can i generate the PR's against the sale order requirement?

Can I plan ROH also in planning table MF50 and then convert the planned order of ROH to PR?

Putting saftey stock in material master is not a good solution otherwise everytime I need to change the safety stock in material master which I dnt wanna do.

Can you give any right method to map this scenario?

Regards

Deepak Sharma