Hi
I hvae done P.O .... and GR has complted against this P.O....in this P.O enter basic price and ..fright value ... but unfortunatily ..i have enterd wrong value for fright condition... now i want to change this fright value in condition tab... but thi s in disable mode.... ( GR completed for this P.O)..
can we change this fright vale...pls help me ..in this issue
regards
sesidhar
hi,
u cant change the freight value. either u have to maintain it in unplanned delivery cost or u can put it in GL account at the time of MIRO.
regards
jash
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
You can't change the freight value after GR done.
Reverse the GRN and create a new line item in the PO(delete the old line item after creation) and insert your freight value and do the GR.
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
No, You can't change the frieght value as gr is completed. You have to reverse the gr , change the value and then again do the gr.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.