P.O condition value change error

Former Member
0 Kudos

Hi

I hvae done P.O .... and GR has complted against this P.O....in this P.O enter basic price and ..fright value ... but unfortunatily ..i have enterd wrong value for fright condition... now i want to change this fright value in condition tab... but thi s in disable mode.... ( GR completed for this P.O)..

can we change this fright vale...pls help me ..in this issue

regards

sesidhar

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

hi,

u cant change the freight value. either u have to maintain it in unplanned delivery cost or u can put it in GL account at the time of MIRO.

regards

jash

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi,

You can't change the freight value after GR done.

Reverse the GRN and create a new line item in the PO(delete the old line item after creation) and insert your freight value and do the GR.

Regards

Former Member
0 Kudos

No, You can't change the frieght value as gr is completed. You have to reverse the gr , change the value and then again do the gr.