heuristic

31 Views

i have a product A which is a FERT. it has two child HALBS B and C. i have defined planning procedure as 3 and heuristic for all the 3 as planning of standard lots. in the product view when i click on product heuristic for the header it is generating planned order. but the BOM is not exploding and the child B and C the planned order is not created. if i go to individual product and click on product heuristic it is taking and creatring planned orders. My requirement is to explode the BOM and create the planned orders at all levels. pls guide.

Thanks

Vinay