on 04-28-2009 12:14 PM
Hi
How to create the budget yearwise in CJ30, can anybody help me to create.
Thanks
S.Murali
Hi,
Check in your budget Profile ( OPS9) if ''Annual" is ticked. If yes, then it allows budgeting year wise.
Also check time frames --> Past Future and start.
Regards,
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
Thanks for your answer
As you mentioned earlier all settings are done already.
For example I am entering the budget values for 2007, 2008 and 2009.After entering the values i am trying to do the Total up , but the Totalup function is display mode. Without the overall value the system not allow me to save the budget. If I enter the overall value manually it is allow me to save.
Now my question is how to calculate the overall value automatically(Example Totalup ).
Thanks
S.Murali
Hi
Thanks for your reply
In my last reply i have mentioned automatically , that means via Toatlup function only. I am not mean system will calculate automatically.
After enter the annual values for Project (Not WBS element), I am trying to Totalup the annual values to overall values. But the Totalup menu is in display mode.
Thanks
S.Murali
Thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Go to CJ30 select the project no and select the WBS no and choose the year e.g 2009 and enter the budget value but you need to tick the Annual values in OPS9 then only you can see the years field in CJ30.
Muzamil
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
98 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.