WBS - WIP / COS CALCULATION

147 Views

Hello,

We generally use for WBS Ra key S0001 method 14 RRB (resource related billing).

Normally when you have costs in progress on WBS (not yet invoiced), the system calculate a wip at the

end of the fiscal period (KKAJ).

I you make an invoice (with DP90) for this costs at the next period, the system must cancel the previous wip and put the costs in the status COS ( cost of sales ).

Since we migrate from 4.5b to ECC6 we have big problems because invoices don't cancel the wip

anymore.

Can you help us?