Dear All
I have one issue regarding Scheduling
1.we have one FG, one SEMI FINISHED material and one RAW material.
2.The In house production days for FG is One day. if demand is given on may 15th,the schedule date for FG is 14th may,upto here it is clear.
3.SEMI FINSHED material is produced by vendor i.e. SUB COTRACTING process. The planned delivery time is two days. the requirement is on 14th may ,so the release date should be on 12th may and delivery date should be 14th may. am I correct?
4.DEMAND is given on 15th may, run the MRP, Planned order is generated for FG and SF. The Schedule start date for FG is 14th may, it is correct.
5.The issue is for purchase requisition, the release date on 13th and delivery date on 15th may, because of this total scheduling going wrong.
Pl give the solution for this issue so that system will give proper release date and delivery date.
If any configuration s thr or not?