on 04-28-2009 7:39 AM
hi
when my maintenance order is in status TECO it allows me to do service entry sheet.But according
to my view it should not allow in standard sap.It is because service entry sheet is technical acceptance
by maintenance people.So you complete the service entry sheet and make the order TECO.Please
explain me in detail.
regards
sanjay
I also faced same problem, i have controlled thru user status.
but it need to maintain manually.
SS
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
thanks for reply
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
A service entry sheet is basically a goods receipt. Any goods movements and FI postings are allowed in the TECO status. Only CLSD (business closed) status will stop these unless you alter the status configuration.
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You use the technical completion of an order to define the following information for the order:
u2022 The order obtains the status Technically completed. The order is marked as complete for Plant Maintenance.
u2022 Now you can only make the following changes:
o Lock and unlock the order
o Set the deletion flag
o Post goods receipts for the order
u2022 You can still enter confirmations for a technically completed order. In order to prevent this, you must create a user status that does not permit confirmations.
u2022 The storage location and account assignment data entered for the order are fixed and can no longer be changed. However, the order can still receive costs, for example, through incoming invoices for materials delivered and used.
If no settlement rule has yet been maintained for the order, the system creates one automatically. If missing data makes this impossible, the system takes you to the screen for maintaining the settlement rule.
u2022 All the existing purchase requisitions for the order are flagged for deletion.
u2022 All the existing reservations for the order are cleared.
u2022 All outstanding capacities which have been scheduled for the order are cleared.
u2022 All the notifications for the order are also completed, unless prevented for one of the following reasons:
o The Complete notifications indicator was not set in the Complete dialog box.
o One or more tasks have not been completed.
o A user status in the notification prevents it from been completed.
u2022 If the order was created using a maintenance plan, the date of the technical completion will be used for the further Scheduling of the Maintenance Plan.
You can make changes to the maintenance process procedure when completing orders. You can, for example, prevent all users that are allowed to complete orders and notifications from using this data simultaneously to change the scheduling of maintenance plans. For more information, see Separate Completion of Maintenance Call Dates
- Pithan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.