Hi Experts,
My Production Plan is freezed for 3weeks hence i cannot incoprate any production within 3weeks. Hence i need to generate a production order for the 4th week however if i put the inhouse production time as 4 weeks the start date of the production order is suggested 28days before the finish dat.Acutal time taken to manfucature the material is 2days.In short i need to create a production order 4weeks ahead and schedule start as 2days before finish date.
Regards
Byju