My scenerio is operation substracting:
1. Control key PI02
2. In opl8 for order type - plant combination, the Reservation / pur. is 2 (from release)
If I create operation before release order purchase requisition is created.
If I create operation after release order purchase requisition is NOT created. (because Reservation / pur =2)
Is there any way to create purchase requisition in this case?
With production order is possible to use functions>activate purchase requisitions /reservations but in processs orders doesn´t exist.
Thanks in advance