Dear Experts,

We have a finished material FM which has two alternative BOMs A1 and A2 . We have ran standard cost estimate SCE1 for the material FM with alternative BOM A1 and created a production order P1. Again we have ran standard cost estimate SCE2 for the material FM with alternative BOM A2 and created a production order P2.

Now our requirement is that when confirmation and GR for the order P1 should update the price as per SCE1 and P2 should update the price as per SCE2 . Please tell how to carryout this in the system.