Former Member
Apr 25, 2009 at 05:42 AM

cost

22 Views

Dear All,

In my project to a digging activity (2days time) , I have assigned work center as set1 which contains 2nos. activity type in costing tab named AT1 and AT2. Thru KP26 , I have assigned rates to these activity types as 100 and 200 per hour. Now in project builder screen , when I am assigning work center set1 to my activity digging , it is also asking for activity type . What should I give : If I am giving AT1 , plan cost is coming 1600 and if I am giving AT2 , plan cost is coming 3200 , Whereas as per scenario plan cost should come as 1600+3200 = 4800? What may be the reason?

Regards,