Dear Experts,
I am using 0PS_C041 info cube to get WBS element Actual cost,
in ECC, PS consultant posted Actual cost USD 250,
when i check it in RSA3, it is showing Two records (Debit & Credit)
wbs123 ....... costelement XYZ ........ S ..... 250
wbs123 ....... costelement XYZ ........ H ..... -250
-
Total ........................................................0
-
because of the two debit credit (S & H) records the total Actual Cost is becomes ZERO, this is the problem.
I am using the Standard RKF for Actual Cost, in that there is no restrictions on the Sender Receiver Indicater field (S & H)
kindly throw some light on me regarding this.
Thanks in Advance
Regards
Reddy Amar
Edited by: ReddyAbi7 on Apr 24, 2009 3:48 PM
Edited by: ReddyAbi7 on Apr 24, 2009 3:48 PM
Edited by: ReddyAbi7 on Apr 24, 2009 3:50 PM
Edited by: ReddyAbi7 on Apr 24, 2009 3:57 PM
Edited by: ReddyAbi7 on Apr 24, 2009 3:58 PM
Edited by: ReddyAbi7 on Apr 24, 2009 3:59 PM
Edited by: ReddyAbi7 on Apr 24, 2009 4:00 PM
Edited by: ReddyAbi7 on Apr 24, 2009 4:00 PM