Hello experts,
I use network orders in my company.
When I delete the header planned order, then SAP doesn't delete the secondary planned order for componants.
Is there a possibility ?
In fact I would like to run MRP for a lower level compared to the second level, but if planned orders are still in the system it is not interesting for me. I mean it won't take into account what I deleted as "head" planned orders.