on 04-24-2009 11:50 AM
Dear Guru's,
BOM of material A is made inactive at header level on 06.03.2009. All the components in the BOM are assigned to MRP area. Now we have one planned order (i.e. stock order - 12.03.2009) for material A. The procurement proposals for components are not coming at plant level but they are coming on MRP area level. As BOM is inactive at plant level then the components should not be planned via MRP at plant level but as there is only one BOM then how procurement proposals are created even at MRP area level? What should be the settings to stop generation of procurement proposals at MRP area also? It is possible to mark deletion indicator at MRP area in MRP1 view.
Please help.
Regards,
SAP CONS
Thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Can you please let us know , how did u manage to achieve the procurement proposals at MRP area level
We have similar requirements, & are able to achieve the proposals at Plant MRP area level only.
Whereas we need at Storage location MRP area level
Thanks & Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Check the PldOrd's components list. Does it contain the components of the BOM? If yes, the requirements for components coming from here...
You can delete the PldOrd, run MRP again and let's see whether you will have any components from the BOM in the newly created PldOrd. If the BOM is really inactive and you have no alternative, active BOMs, the PldOrd shouldn't have any component in its components list.
Regards,
Csaba
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.