Dear All,
Flow is as follow.
0. While performing MFBF-Make-To-Order with Planned Order and Material as input field and save in component screen, I am getting error "Enter WBS Element".
1. Material is with Planning strategy: 85
2. Material is attached to WBS->Network->Activity (Internal)->Material Component in CJ20N-Project Builder
3. Requirement is generated with MD51 for WBS Element and thus Planned Order created with A/c assignement Category: Q, Special Stock: Project Stock, Consumption: Project
4. Now Step: 0 is performed
Actually, in component screen in MFBF, WBS Element column in grid is blank and disabled and components are with 261/Q.
Please propose the solution, if any body worked on above scenario.
Regards,
Tanuj Parikh