Hi all,

I have a query regarding FERT.

Here at the client end, we are having a scenario, listed point wise below:

1. Industry is a Chemical Industry.

2. FERT is manufactured in a continuous process, hence Production Dept. is not sure about the despatch qty. and packing material at the time of production order creation / confirmation.

3. The FERT over here is actually treated as a HALB, and the Qty. which will get despatched along with the Packing Material is treated as FERT, hence to convert HALB to FERT, there is a production order generated, whose BOM contains HALB + Packing Material and Routing contains Packing Operation.

-


Problem faced in PP:

1. Production is not sure which is the packing mtrl. and hence need to create an extra Production Order, just to convert this HALB to FERT.

2. More than 1 Material Code exists for FERT, i.e. as per the Type of Packing Material.

3. At the time of Reporting for a FERT, they have to refer more than 1 material code.

Query

How can we map Different Packing Material for FERT with a Single Material Code ?

Thanks in advance,