Hi all
This is a KANBAN scenario - with external replenishment strategy
Standard SAP KANBAN only triggers a purchase order(and not a purchase requisition) when the status of the bin is set empty
Client wants a check before the order is released
So we suggested for release strategy
Now what the requirement is,single PO has to be created per vendor for all the materials he will supply
Already PO will be created by the system,when the status of the KANBAN will be set "EMPTY"
Is there any way that we can combine PO's and send as one single PO
Please let me know the possibilities
Thanks