Hi all

This is a KANBAN scenario - with external replenishment strategy

Standard SAP KANBAN only triggers a purchase order(and not a purchase requisition) when the status of the bin is set empty

Client wants a check before the order is released

So we suggested for release strategy

Now what the requirement is,single PO has to be created per vendor for all the materials he will supply

Already PO will be created by the system,when the status of the KANBAN will be set "EMPTY"

Is there any way that we can combine PO's and send as one single PO

Please let me know the possibilities

Thanks