Hi all,

*I am not sure if someone can help me.*

*I am using cProjects suite 4.5, when I create a project ( in cproject) error message 'The settings for accounting integration contain errors' Message no. DPR_FIN_GECCO004 appears and the accounting tab is empty.*

*I am not sure where can be the problem, I have reviewed cproject configuration and I think it is correct.*

*Does anyone have a configuration guide? or at least may someone tell me what he has configued at this point IMG --> collaboration project -->Conection to external system -->Object link in sap system --> Make settings for calling a sap transaction -->Alias for the web server of a SAP transaction ?*

*Thank you very much for your help.*

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

3 Answers

  • Best Answer
    avatar image
    Former Member
    Apr 24, 2009 at 08:26 AM

    Hi Sara,

    Please go through the following link. It will be helpful for configuration of cProjects.

    http://help.sap.com/SCENARIOS_BUS2005/helpdata/EN/d8/0d134e26b6ce43a03c09bcc12ba58b/frameset.htm

    Regards

    Yogesh

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Apr 27, 2009 at 05:27 AM

    Hi,

    1.First define the cost/revenue rates used in costing.

    2. Second imp activity is replicate cost revenue rates to R/3 system. if you using same system give RFC destination NONE. otherwise use your target system available to you. take help of basis if u dont know traget system. Activity given below when u replication cost revenue rates.

    Activities

    Enter the replication line and specify which rates you want to replicate under Selections.

    If you do not specify a selection, all rates are replicated.

    If you want to replicate the records only partially, and you do not want to post them in the target system, set the Test Run indicator.

    After test run sucessful, plz uncheck that test rum box and replicate.

    Thanks

    Amit

    note: award points for useful answer

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Apr 27, 2009 at 09:55 AM

    Hi,

    Thank you very much for help me. I have already found my problem. In the ERP ( IMG --> Integration with other SAP components --> Controlling scenario --> my cproject type was related to internal order instead a WBS) I have changed it and the error message has dissapeared.