Hi All,

I am running MRP Run where client requirement is stock transfer order should not be considered. This stock transfer is for finished goods materials. Stragegy used 10 Net requirement planning.

Example

1. Plant 1000 is production plant where MRP Run execution is happen.

2. Plant 2000 is depot where materials is stored.

3. Plant 2000 is raising stock transfer order for 1000 plant.

4. In requirement details list MD04 stock transfer PO is appear with status like for 1000 plant ORD DS in mrp element and in 2000 plant status is POitem.

5. Here in sending plant 1000 due to ORD DS order system is considering this for net requirement calculation.

6. With Plan Independent Requirement PIR system also considering this requirement for net requirement calculation.

example

Lets PIR of X material is of 1000 EA

Stock transfer order is of 500 EA

After MRP run system is giving requirement of 1500 EA.

7. As per client requirement, stock trnasfer order should not be considered for MRP net requirement calculation.

8. Here for above case materials Availability check is KP No Check is maintained.

In above given case stock transfer order is exclude from MRP run. Plz suggest solution.