Dear SAP PS EXPERTS ,
We have a problem !
We are creating a project in simulation mode CJV1 and attached materila component to the same so I am getting the costs for the projects.
Next I go to the CJV4 I have created the operative project
then I create the buget for the same, give the same buget as the commited costs of the materials ,
But when I am try=ing to relase the budget the system says the budget exhausted????
I am not able to release any budget for the operative project.
What should I do???
regards,