Dear SAP PS EXPERTS ,

We have a problem !

We are creating a project in simulation mode CJV1 and attached materila component to the same so I am getting the costs for the projects.

Next I go to the CJV4 I have created the operative project

then I create the buget for the same, give the same buget as the commited costs of the materials ,

But when I am try=ing to relase the budget the system says the budget exhausted????

I am not able to release any budget for the operative project.

What should I do???