1.Factory calender is maintained and assigned to the plant,SUNDAY is
not working day for Client,so the system is not planning any internal
activities for SUNDAY,up to here it is fine.
2.One semi finished material is produced by vendor.i.e.Sub contracting
process, it takes 2 days to complete.For vendor SUNDAY is not a
working day.
3.Planned delivery time is maintained as 2 days ,so that if PO is
release on MONDAY ,the delivery date on WEDNESDAY.
4.If requirement is on MONDAY ,In MRP Run System is generating the
release date on SATURDAY and delivery date on MONDAY,here system is
taking the calender days not the factory calender days,Client is
asking for correct delivery date.
5.Is there any way to tell the system that SUNDAY is not working day
for vendor,so that system will generate the release date on FRIDAY
and delivery date on MONDAY.
Please give your valuable inputs.