Regarding planned delivery time for Subcontracting process

272 Views

1.Factory calender is maintained and assigned to the plant,SUNDAY is

not working day for Client,so the system is not planning any internal

activities for SUNDAY,up to here it is fine.

2.One semi finished material is produced by vendor.i.e.Sub contracting

process, it takes 2 days to complete.For vendor SUNDAY is not a

working day.

3.Planned delivery time is maintained as 2 days ,so that if PO is

release on MONDAY ,the delivery date on WEDNESDAY.

4.If requirement is on MONDAY ,In MRP Run System is generating the

release date on SATURDAY and delivery date on MONDAY,here system is

taking the calender days not the factory calender days,Client is

asking for correct delivery date.

5.Is there any way to tell the system that SUNDAY is not working day

for vendor,so that system will generate the release date on FRIDAY

and delivery date on MONDAY.

Please give your valuable inputs.