hi all,
we have the foll scenario, we create WBS element and flow budget in CRM, same gets transferred to ECC. foll are the settings , we have maintained for avl ctrl in ECC - PS
tolerance limit:
Tr gp: ++, action = 1, usage = 90
budget profile:
activation type = 1, checked overall and releases button.
i had created the WBS element in crm and then it got transferred to ECC. havent flown any budget. after some time, i had flown budget in crm, same is reflecting in ECC, but status is only REL. AVAC status was not set. So i had manually set it using CJ32.now tried creating PR/PO, worked fine.( why AVAC status doesnt get set, when budget is flown????????????)
now here is my requirement. availability ctrl gets activated only when, there is a bugdet. our users generally create the WBS element, but dont flow any budget temporarily. so for these elements, users can create PR/PO without any problem, as availability ctrl doesn't get activated. Pls suggest as to how to activate availability ctrl, even if the budget is 0.
Pls help.
Rgds,
Anitha J