Aggregation level ZFI_FINGL is locked by the Change and Transport Organizer

Former Member
0 Kudos

Dear,

After transport from a dev to prod system I get this message on the planning modeler :

"System is not set to changeable - objects are not changeable

Aggregation level ZFI_FINGL is locked by the Change and Transport Organizer"

Do you know how to fix it ?

Thanks in advance,

Thibaut

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Hi.

In dev system goto "Transport Connection". In upper tollbox you will see "BEx" button.

Press this button and assign request to your project.

Regards.

Former Member
0 Kudos

Hi, this error message can be quite misleading. The issue shows up if an Aggregation Level is not included in any transport request. Go to the transport connection and collect the aggregation level on a transport, afterwards you will be able to edit the aggregation level in RSPLAN.

Regards

Claas

Former Member
0 Kudos

Hi,

By default the planning modeller configuration is added to the standard BEx transport (if it is not saved in $TMP). If there is not one set up then create one in the admin workbench transport connection.

If you don't use this, then you can add the objects you wish to change manually into a transport before you change them - this also works.

Cheers