We are using the program PPSFCACT to qutomatically TECO the order. The value maintained in the "Exceeding of delivery date" is 2 days.
System does not seem to be considering this 2 days tolerance at all
Some ex:
1) Order 1 : Basic and scheduled finish date : 04.04.2009. Order TECOed on 07.04.2009 - reason final confirmation flag was send on the 06th
2) Order 2 : Basic finish date - 04.04 and scheduled end date 03.04.2009. order TECOed on 04.04.2009 - reason final confirmation flag was set on 03.04.2009
Question : What is the use of the expected delivery date in this program