Dear all,

Ours is a MTO scenario , with strategy 81.

so, the system creates a planned order for FG during sale order creation.

During MRP run (Lead Time sched) , system creates Planned Orders for SFGs.

Here , system schedules the SFG order simultaneously as that of FG.

ie, Sale Order date - 10.05.09 , system schedules orders of both FG & SFG on 10.05.09

System is not scheduling backwards right from Sale order date to Fg and then SFG.....based on values from routing .

The following settings are in place.

- Inhouse prodn times not maintained in material master / operation setup/proc time values maintained in routing

- OPU3 / OPU5 Adjust Basic dates/Dep reqmts to operation start

kindly give valuable inputs.

Regards,

Sheik