Dear all,
Ours is a MTO scenario , with strategy 81.
so, the system creates a planned order for FG during sale order creation.
During MRP run (Lead Time sched) , system creates Planned Orders for SFGs.
Here , system schedules the SFG order simultaneously as that of FG.
ie, Sale Order date - 10.05.09 , system schedules orders of both FG & SFG on 10.05.09
System is not scheduling backwards right from Sale order date to Fg and then SFG.....based on values from routing .
The following settings are in place.
- Inhouse prodn times not maintained in material master / operation setup/proc time values maintained in routing
- OPU3 / OPU5 Adjust Basic dates/Dep reqmts to operation start
kindly give valuable inputs.
Regards,
Sheik