Hi,
In my project, for one of the WBS, plan value is Rs.12701991, actual value is Rs,1666280 and commitment is Rs. 9520761 so acutal + committment = Rs.11187041 which is already exceed by Rs,1514850 wrt plan. Still in remaining plan value system is showing Rs. 1931965.
How can it possible?? because of remaining plant value, my budget is getting exceeded.
Regards
Kalpesh