Hi all

The requirement is like this

Normal subcontracting cycle - Subcon PO and then 541

After that i did inbound delivery in VL31N for the subcon PO , Here iam getting the finished goods line item so that i can enter the delivery qty and serial number for the finished componenet

My query is , Is there any possibility of exploding the BOM and entering the serial number for the assembly level materials in the inbound delivery itself.

After that based on inbound delivery i can do GR , Your inputs pls