Hi experts,
We have finished good ''A'' and raw material ''B'' having longer procurement time.
After mrp run,for material "A"planned order get generated and PR for "'B''also.
Planned orders start date and end date suppose 22.04.2009 and 23.04.2009.But PR date for "B'' are
26.04.2009 .That means the material will not be available for the planned orders in the scheduled date.
This is the results of MRP.
But the requirement is by checking the last raw material availability date system should reschedule the planned order after 26.04.2009 automatically.
Thanks in advance.
Regards
Vilas