Factory Calendar and Lead Time Scheduling of Planned/Production Order

894 Views

Hi All,

We have following business requirement from client for SAP PP implementation project:

We have a Production Plant running 24 X 7 but our finished products are shipped only from Monday to Friday. In order to restrict shipment planning on Saturdays and Sunday we have set Plant level factory calendar with Monday to Friday as only working day. And in the Workcenter capacities tab we have set the calendar ID which has all days as working without any holiday.

Problem comes when we try to create new planned/production order. When we set the Planned/Production Order Start/End date on Saturday or Sunday we get warning message from SAP saying so and so day is not working day so changing the Planned/Production Order Start/End date to next working day.

My question is even though we have maintain calendar ID in workcenter which has all days working why we are getting this message from SAP?

Waiting for clue from experts !! What alternate do I have to address the business requirement?

Eagerly waiting for your valued suggestions.