Hi All,
The SNP Optimizer Network comprises of CDC and the production plant. The resources are in a matrix such that more than one products can be produced in one resource. The storage cost is very low and the SNP Optimiser is creating a distribution demand (planned) and a production planned at production plant which is supplying plant to the CDC.
The demand element at the CDC is approx 1000 units in buckets extending to 24 months in future but the distribution receipt (planned) at CDC, distribution planned & production planned at production plant is extremely high ranging from 20000 units onwards for three buckets one in wk19, wk20 and future wk.
Technically even if the optimizer planned huge quantities in the beginning buckets trying to achieve 100% capacity utilization from a business standpoint we cannot hold inventory of products in earlier weeks for a requirement extending over 24 months.
Could you please confirm if our technical understanding is correct on the behavior of the SNP Optimizer.
Regards,
Prashant Kumar